|
|
Coombe Hill - A Case Study in Golf Course Renovation
by Ken Moodie
JF Abercrombie designed Coombe Hill in 1911. Although he
only designed about six golf courses in his relatively
short career he was well respected by his peers for his
ability
to work with nature and create very natural features.
This is evident in the setting and gentle shaping of the
greens at Coombe Hill which is one of the great strengths
of the golf course.
The contouring of the putting surfaces is a key element
to the strategy of many of the holes since it is important
not just to be on the green but near the flag in order
to be confident of two putting.
Prior to renovation the course, and in particular the bunkers, had fallen into
a state of decline and nature had taken over by the
steady ingress of trees.
The
open heathland character of the course had been lost
and the
greens suffered from shade and a lack of circulation.
Fortunately an enthusiastic Course Manager and
a forward thinking Greens Chairman both wished
to see the golf course restored to its former glory.
A consultant agronomist was appointed to advise
on the improvement of the playing surfaces and
at the same time a woodland and environmental consultant
was brought in to produce a plan to manage the
woodands and to re-establish areas of heathland.
"A
report was developed which reviewed the strategy
of the
course, and of individual holes
in more detail, in order to make proposals for
improvement. It was clear that the framework of
the course was sound and there were 18 strong holes
to be re-discovered."
The trees had grown to such an extent that they
had fundamentally altered the strategy of the original
holes. Some key bunkers had become hidden and the
shot options from many of the tees reduced to one,
namely straight-down-the-middle.
The thinning and removal of trees not only brought
some of the key bunkers back into play, and restored
the spirit of many of the original holes, but also
exposed weaknesses in the bunker layout which had
occurred due to the advances of modern club and ball
technology.
For this reason Creative Golf Design were commissioned
to advise on the redevelopment of the bunkers and
improvement of the strategy of the holes on the golf
course. The Club had suffered with poor and inconsistent
bunkers for a number of years and recognised that
they at least required to be rebuilt. However, it
also realised that consideration needed to be given
to bunker siting given the passage of time since
the original design had been conceived.

A report was developed which reviewed the strategy
of the course, and of individual holes in more detail,
in order to make proposals for improvement. It was
clear that the framework of the course was sound
and there were 18 strong holes to be re-discovered.
Already the course contained four top-class
par 3's which could stand shoulder-to-shoulder
with the very best in golf. These only required relatively
minor tweaking during the bunker remodelling process
to repair wear and tear and accentuate the finest
qualities of the holes.
The three par 5's at Coombe Hill, like
on many courses of the same vintage, suffered from
a lack of length with no room to increase them significantly.
The 4th and 15th holes both possessed downhill drives
and were therefore very reachable in two-shots.
This was not considered a bad thing, since the
opportunity of a birdie or even an eagle, adds greatly
to the excitement of the game. However, it was felt
that two good shots should be required to reach the
green so hazards, in the form of a bunker on the
4th and a grass hollow and mounds on the 15th, were
placed short of the green on the line for the approach
for a long second shot.
These hazards would not unduly challenge the
golfer playing a short 3rd shot to the green but
would add some distance perception difficulties to
the task by creating an area of hidden ground on the approach.
Coombe Hill possesses a fine mix of par 4's.
The changes in elevation throughout the course
provide some dramatic drives from elevated tees
and also lengthen the three uphill par 4's
beyond their measured yardage. Two of the uphill
par 4's - the 8th and the 16th - were identified
for more radical change.
For both holes the impression from the tee was
that they climbed steadily straight up the slope.
This gave them a similarity which detracted from
the golfing experience. The solution was to dogleg
both holes slightly in opposite directions by the
careful placement of bunkers, some judicious removal
of trees and the reshaping of the fairway. With
relatively minor changes the holes have been transformed
giving them an individual identity they previously
seemed to lack.
The 7th hole allowed the opportunity to create
a strategically testing short par 4. The framework
of the hole was already very good but the test
for the better player had been lost. The ingress
of trees had diluted the strategy of the hole and
hidden the approach to the green from the tees.
For what is a driveable par 4, visibility of
the green and at least the approach is essential
to the drama of the hole. With the subtle realignment
and remodelling of the existing bunkers, addition
of a new bunker at 260 yards on a direct line to
the green, and the placement of mounds on the opposite
side of the fairway to narrow the approach, four
distinct landing areas were provided to accommodate
all abilities of golf and levels of risk.
Trees were removed to allow the front of the
green to be seen from the tee. In addition, a new
challenging pin position was created by extending
the green at the back. The best position for the
drive will now depend on where the flag is placed
on a given day.
An important aspect of the proposals was the
decision to retain a number of the shorter drive
and approach bunkers. Although no longer relevant
for the better golfer, they provide a challenge
for other members and add greatly to the composition
of the golf hole. If all the bunkers were to be
shifted to the 230-260 yard range the fun would
be lost for a large proportion of the membership
who would no longer be able to reach them with
their drives and would be well past the bunkers
with their second shots.
The construction work, which consisted of 15
new bunkers, 52 remodelled bunkers, a number of
grass hollows and mounds, two green extensions
and the drainage of the three poorest performing
greens began in October 2003 and was completed
in early February 2004.
The golf course architects visited on a weekly
basis to advise on the shaping of the new features
and to ensure that the Specification was being
followed. This was very important to ensure that
the design plans were realised successfully and
allowed minor on-site modifications to be made
to improve the end product.
It was truly a team effort with Contractor,
Agronomist, Greens Chairman, Course Manager, Woodland
Consultants and Golf Course Architects coming together
for regular meetings to discuss progress, specification
issues and further improvements which could be
made to the planned design. Coombe Hill has benefited
greatly from taking professional advice and a pragmatic
approach to the development of the course.
|