The works have involved the raising and reconstruction of five holes and the installation of a new irrigation system. Works commenced on 15 May 2016 and will be completed on 15 July 2016 when they will be handed back to the Clients maintenance team to complete the establishment of the new holes. Fairway areas have been sprigged and all other areas have been turfed to give the team the best chance to attain the standards demanded of the Tour.
This seemingly impossible timeframe was achieved by undertaking a very detailed pre-project commencement analysis and religiously following the programmed works on a day by day basis. Benedetti-Guelpa have even managed to slip in a new putting green and chipping area at the Clients request without running over the original timeframe.